Budget for a Nursery School in Lenkisem – Kenya
Alarico Valls de Moraes
How I don't have details about the ground I made some considerations:
- Foundation type “radier” like lage armed measuring 10,00 m x 17,00 m and 10cm of depth – reinforcing steel 6,3mm each 15cm in both directions (served as a sidewalk):
- Walls with concrete blocks:
- Roof with tiles of fiber cement – 6cm oh thickness, supported in a wooden structure (guides) 15cm and rafters of 5cmx 7cm;
- Doors and windows with iron;
- Floor with cement smoothed, using the same radier;
- Electrical installation with 6 points of light.
List of Material and Costs:
- 1. Foundation
- Steel 6,3mm: 200 steel bars
- Annealed wire: 20 kg
- Cement: 100 bags
- Sand: 15 m3
- Gravel 12m3
- 2. Walls
- Concrete blocks 1700 -39x19x14
- Sand: 1m3
- Cement:5 bags
- Steel 10 mm, 10 bars ( )
- 3. Roof
- Wooden guides, 1x15 cm x 4,50m : 100 units
- Rafters: 5cm x7 cmx5 m: 35 units
- Nails: 17 x 27: 10 kg
- Fiber cement tiles: 2,44 m x 1,10 m: 70 units
- Roofing screws: 222 units
- Ridge tiles: 30 units
- 4. Miter
- Openings: iron window, 2m x1,60 m : 5 units
- Iron door : 2 units, 0,90 x 2,10
- Glasses: 3mm, 16m2
- 5. Electrical installation
- Double wire, 2x2,5mm: 150 m
- Switch triple: 2 units
- Wallbox: 10 units
- Pvs BOX : external, for distribution center; 1 unit
- Single phase circuit breaker, 15A: 4 UNITS
- Insulating tape: 3 units
- 6. Painting
- Sealer, 5 gallons
- Paint for the walls, the most cheaper, 5 gallons
- Solvent: 1 gallon
The total cost of this material in Brazil is: US$ 20,000
Contribution: Pedro Alexandre Pitella - Civil Engineer